Notice of Hot Water Pipe Replacement and Temporary Closure of the Entire Property
Thank you for choosing Daiwa Roynet Hotel Nagoya Shinkansenguchi. We will be replacing the hot water pipes during the period below as part of our facility maintenance. ■Scheduled Construction Period Monday, December 21, 2026 – Saturday, March 13, 2027 ■Work Hours 8:00 AM – approximately 5:00 PM ■Scheduled Full Hotel Closure Wednesday, January 6, 2027 – Friday, January 15, 2027 ※No work will take place on Sundays or from December 30, 2026 to January 3, 2027. ※Noise and vibrations are expected between 11:00 AM and 2:00 PM during construction. ※Workers will be moving through the hotel and surrounding areas during construction. ※The construction period and work hours may change depending on progress. We apologize for any inconvenience or disruption during construction. All work will be carried out with careful attention to safety. Thank you for your understanding.